Sunday, July 8, 2007

The plan as of 7/8/07

The plan....

Floors - Put in a new 1/2 in. layer of sub floor on top of the existing floor for added stability.

Walls and Windows -
Remove some windows and patch them in with fiberglass and metal studs. Our friend Danny can take care of this part for us, but first we'll chalk in the floor plan and see which windows will need to be removed. We do not want to build OVER the windows, because this is for the long haul, baby.

After the windows are patched, we will insulated the walls, cover them with luon (a thin plywood), cover the luon with carpet and cut in new smaller windows...and vents for the stove, microwave and hood. (update: we did patch four side windows, but left the other four as is - no new windows - although it still technically could be done if needed).


Propane -
Weld in a box for the propane tank and water tanks. We are brainstorming the best location for these things. Can we build storage under the bus??? Everything is an option, when nothing is what you've got.

No comments: